Remove everything related to the connected environment count for project
status. We decided that because we don't have anywhere to link it to at
the moment, we don't want to show it yet.
This PR adds stale flag count to the project status payload. This is
useful for the project status page to show the number of stale flags in
the project.
This PR moves the project lifecycle summary to its own subdirectory and
adds files for types (interface) and a fake implementation.
It also adds a query for archived flags within the last 30 days taken
from `getStatusUpdates` in `src/lib/features/project/project-service.ts`
and maps the gathered data onto the expected structure. The expected
types have also been adjusted to account for no data.
Next step will be hooking it up to the project status service, adding
schema, and exposing it in the controller.
This PR adds more tests to check a few more cases for the lifecycle
calculation query. Specifically, it tests that:
- If we don't have any data for a stage, we return `null`.
- We filter on projects
- It correctly takes `0` days into account when calculating averages.
This PR adds a project lifecycle read model file along with the most
important (and most complicated) query that runs with it: calculating
the average time spent in each stage.
The calculation relies on the following:
- when calculating the average of a stage, only flags who have gone into
a following stage are taken into account.
- we'll count "next stage" as the next row for the same feature where
the `created_at` timestamp is higher than the current row
- if you skip a stage (go straight to live or archived, for instance),
that doesn't matter, because we don't look at that.
The UI only shows the time spent in days, so I decided to go with
rounding to days directly in the query.
## Discussion point:
This one uses a subquery, but I'm not sure it's possible to do without
it. However, if it's too expensive, we can probably also cache the value
somehow, so it's not calculated more than every so often.
This change introduces a new method `countProjectTokens` on the
`IApiTokenStore` interface. It also swaps out the manual filtering for
api tokens belonging to a project in the project status service.
This PR adds member, api token, and segment counts to the project status
payload. It updates the schemas and adds the necessary stores to get
this information. It also adds a new query to the segments store for
getting project segments.
I'll add tests in a follow-up.
This PR adds connected environments to the project status payload.
It's done by:
- adding a new `getConnectedEnvironmentCountForProject` method to the
project store (I opted for this approach instead of creating a new view
model because it already has a `getEnvironmentsForProject` method)
- adding the project store to the project status service
- updating the schema
For the schema, I opted for adding a `resources` property, under which I
put `connectedEnvironments`. My thinking was that if we want to add the
rest of the project resources (that go in the resources widget), it'd
make sense to group those together inside an object. However, I'd also
be happy to place the property on the top level. If you have opinions
one way or the other, let me know.
As for the count, we're currently only counting environments that have
metrics and that are active for the current project.
This was an oversight. The test would always fail after 2024-11-04,
because yesterday is no longer 2024-11-03. This way, we're using the
same string in both places.
Adding project status schema definition, controller, service, e2e test.
Next PR will add functionality for activity object.
---------